State Building Inspection Summary - Single Story with Basement or 2 Story

Single Story with Basement or Two Story

  1. FOOTING - Inspect footing before concrete is poured.
  2. STUB OUT - 1st rough plumbing within the gravel before pour.
  3. 1st STORY WALL - wall and corresponding footing drainage lines.
  4. ROUGH PLUMBING - Piping to appliance locations, vent stack, etc.
  5. FRAMING
  6. SHEETING - Initial exterior wall coverings and roof decking, if ready
  7. ROOF - Decking, or final if ready
  8. BUILDING FINAL - Exterior and finished interior walls, final plumbing, exterior site clean up, windows and doors installed

 

Minimum Site Visits for the following:

  1. FOOTING
  2. STUB OUT
  3. 1st STORY WALL
  4. ROUGH PLUMBING, FRAMING, SHEETING, ROOF DECKING
  5. ROOFING FINAL, BUILDING FINAL, SITE FINAL

 
Fees:

  • Minimum Permit Fee - $150.00
  • Re-Inspection Fee - $25.00 per inspection

 

Further Requirements:

  • A Plan Review is to be conducted by the City Manager.

 

  • Tax Parcel Map from Property Assessor with building footprint superimposed will be used to determine compliance with zoning ordinances.
  • Sketch of front elevation is required.
  • Wall, floor and ceiling framing information is also required.
  • General plumbing layout will be needed.

 

PENALTIES:

The penalty for continued non-compliance will be a $50.00 Fine, plus $25.00 Re-Inspection Fee, and no further inspections or Certificate of Occupancy until fine is paid and re-inspection is passed.

City of Waynesboro, Tennessee
P.O. Box 471
122 Public Square East
Waynesboro, TN 38485
(931) 722-5458
(931) 722-9109